Time and Work Level 2 Practice Quiz: Efficiency, Wages and Alternate Days
This Time and Work Level 2 set tests multi-worker problems where men, women, boys, machines or conveyor belts share a single job. It covers pair work rates, workers leaving or joining midway, wage sharing and alternate-day working. Aptitude360 provides a worked solution for every question so you can check each method step by step.
Topics covered in this Time and Work set
- Comparing the work capacity of men, women, boys and children
- Work done by pairs such as A with B, B with C and C with A
- Workers joining, leaving or being replaced partway through a job
- Workers with different daily working spans and their combined output
- Dividing a fixed payment by work done, and earnings from daily wage rates
- Alternate-day working and helpers who assist on fixed days
- Printing machines and conveyor belts working at different rates
Key formulas and rules for Time and Work
- Work equation: \( W=R\times T \)
- Two workers together: \( T=\dfrac{ab}{a+b} \)
- Pair sums: \( (A+B)+(B+C)+(C+A)=2(A+B+C) \)
- Same job, equally efficient workers: \( M_{1}D_{1}=M_{2}D_{2} \)
- Fixed total pay \( P \) split by work done: \( S=\dfrac{w}{W}\times P \)
Revision tips for multi-worker problems
- Take the total work as the LCM of the given days so that daily rates become whole numbers.
- When men, women and boys work at different capacities, convert everyone into one unit of efficiency before using the man-days rule.
- If daily wage rates are given, multiply each rate by days worked instead of splitting the pay by work share.
- In alternate-day questions, find the work done in one full cycle, then handle the leftover days separately.
Who this Level 2 set suits
This set suits quant aspirants who already know basic time and work and now want practice on mixed-worker, wage and alternate-day variations.